Why apply for funding now?

Modernisation can reduce electricity use and maintenance. The benefit depends on the existing equipment, operating hours and planned lighting levels. Consider funding early, alongside a realistic financial assessment.

Current funding programmes

The Municipal Guideline of Germany’s Federal Ministry for the Environment, Climate Action, Nature Conservation and Nuclear Safety (BMUKN) supports outdoor and street-lighting upgrades. Zukunft – Umwelt – Gesellschaft (ZUG) gGmbH administers the programme.

Distinguish grants from financing

ProgrammeFunding bodyFundingScopeSource
KommunalrichtlinieBMUKN / ZUG25%Share of eligible expenditure.NKI
Municipal Guideline: higher rateBMUKN / ZUG40%For financially weak municipalities and eligible applicants in lignite mining regions.NKI
IKK 208KfWLoanMunicipal investment financing; not an additional grant.KfW
IKU 148KfWLoanFinancing for municipal and social enterprises; check project-specific terms.KfW

Scroll horizontally to see all columns.

Adaptive control does not automatically increase the grant rate. Do not simply add other grants: check combination rules, own contributions and state-aid limits for the specific project.

Requirements and evidence

For streets, the programme requires zone-based and time- or presence-dependent control, with exceptions for certain applications. Switching to LED or using a particular product interface alone does not establish eligibility.

The technical annex requires, among other things, replaceable modules and control gear, suitable light distribution and a maximum of 3,000 kelvin for street lighting. Incorporate all applicable requirements into the design.

Read the technical annex (PDF)

How an application works

  1. Survey the existing installation

    Record luminaires, power, operating hours and energy use. Calculate the planned savings and investment.

  2. Check eligibility

    Check applicant, measures and expenditure against the programme. Discuss uncertain cases with ZUG in advance.

  3. Apply online

    Prepare the calculations in KRL-Online and submit the application through easy-Online.

  4. Approval and implementation

    After approval, implement within the specified deadlines and document the required evidence.

Costs and payback

Illustration, not a project forecast: a €600,000 investment that is fully eligible and a 25% grant leave an own contribution of €450,000. Assumed annual energy and maintenance savings of €120,000 give a simple payback of 3.75 years. Financing costs, price changes and replacement investments are excluded.

Modernisation investment
€600,000
Grant
€150,000
Own contribution
€450,000
Payback of own contribution
3.75 years

Common mistakes to avoid

Common risks include ordering too early, assuming an unverified grant rate, missing baseline data and designing without suitable controls. An interface such as Zhaga Book 18 describes technical compatibility; it is not a funding certificate.

Conclusion

First establish the existing conditions and planned measures, then assess funding and financial viability. Whether to retrofit or replace a luminaire depends on the project. ENVIOTECH can help assess the technical options.

Sources checked on 9 October 2026. The applicable guidelines and the funding body’s decision are authoritative.

Frequently asked questions

Does adaptive lighting automatically receive more funding?

No. The higher rate depends on applicant eligibility, not solely on the type of control.

Are retrofit solutions automatically eligible?

No. Retrofitting controls and replacing a light source are different measures. Check the specific measure and all technical conditions.

Can funding be combined?

Only within the rules of the respective programmes. There is no universal combined grant rate.

Last updated on .